Week of June 30
General contractors Andrew Mancini Associates completed demolition of wood floors; demolition of bathrooms continues. Metal ceilings in the science rooms were removed, as well as classoom windows in the 1986 addition. Contractors began replacing windows.

DiGesare continued working on temperature control wiring, and started installing controls. Steam trap and hot water valve replacement began. Nelcorp continued installing light fixtures, occupancy sensors and exit lights throughout the building, and began running conduit on the roof for exterior lighting.

Mid-Atlantic completed asbestos removal in the library, and began prepping Room 223 for floor tile removal.