Week of Aug. 4

Andrew Mancini Associates started block wall construction in the bathrooms. The glazed tile replacement in cafeteria was completed. The plaster ceiling in the cafeteria was painted.

Ceiling grid was finished in the basement hallway and started in the new classrooms. Window replacement moved to the Main Street side of the building. In the library, work continued patching plaster, building walls, and installing the original trim around the ceiling. Underlayment was poured in all the first-floor rooms and vinyl tile started on the second floor.

Digesare continued replacing and wiring steam valves and traps. Workers tested the heating pipes to the bathrooms and new classrooms and insulated them. Duct work was started for the new classrooms, cafeteria, kitchen and bathrooms.

Nelcorp continued fire alarm installation and started conduit for the sound and theater lighting in the cafeteria.

Tri-Valley continued plumbing rough-in in the bathrooms.

Asbestos - Midlantic removed the rest of the windows and glass block on the south side of the building which completes their work. They have demobilized and have left the site.

Print This Article
footer logo
Schenevus Central School District
159 Main Street, Schenevus, NY 12155
Phone 607 638 5881 | Fax 607 638 5600
facebook
5210 Every day!
bassett healthcare network
© 2017. All Rights Reserved. Schenevus Central School District.