Week of June 23
General contractors Andrew Mancini Associates continued wood floor removal in the old school classrooms. They also started demolition, removing toilet partitions from four bathrooms, and removing bleachers and backstops in the cafetorium. The stage wall and floor were cut out to allow for the handicap lift installation.

Tri-Valley Plumbing & Heating continued demolition of old plumbing from the old school bathrooms. DiGesare continued work on temperature control wiring. Removal of the cafetorium air handler was started.

Nelcorp Electrical Contracting continued to install light fixtures, occupancy sensors and exit lights throughout the building. Mid-Atlantic finished prep work in the library for asbestos removal, and carefully removed the wood trim from the ceiling perimeter for re-use.