Week of July 28

Andrew Mancini Associates had their excavator on site removing sidewalks and pole bases. New pole bases were poured and granite curbs installed. Window installers moved to the east side of the building replacing windows. Ceiling and walls were constructed and plaster patched in the library. Windows and drywall have been installed in the new classrooms.

Digesare continued replacing and wiring steam valves and traps. New circulating pumps were installed in the boiler room.

Nelcorp installed new lights and fire alarm in the cafeteria. Electric rough-in continued in the library area. Workers removed the old light poles in the parking lot and ran conduit for the new light poles.

Tri-Valley continued plumbing rough-in in the bathrooms.

Midlantic removed floor tile in room B04 and started window removal on the east side of the building.