Week of July 21
Andrew Mancini Associates completed the ceiling grid, continued tile replacement, and started the new stage rigging for lights and curtains in the cafetorium. Workers started framing walls and ceilings, refinishing woodwork, and constructing the platform in the library area. Window installation is complete on the west side of the old building. Work began in the courtyard, and on the new access control system.

DiGesare continued installing valves, steam traps and controls throughout the building. Workers completed demolition of the air handler for the cafetorium.

Nelcorp completed installation of the gym lights and exterior lights, and began installing lights on the cafetorium ceiling.

Tri-Valley continued roughing in vent and waste lines in the bathrooms. Mid-Atlantic continued window removal, completing the courtyard area.  Workers removed floor tile in Room 115, and prepped B04 and the windows on the Main Street side of the building.