Week of July 14
Andrew Mancini Associates continued window installation on the west side of the building. The masons finished brick work on the exterior of the new classrooms. Workers continued refinishing library woodwork. Floor leveler was pumped into all the rooms on the second floor. Work began to replace damaged wall tile, and build the ceiling grid, in the cafeteria.

DiGesare installed energy-efficient oil burners on the boilers. Workers continued installing new valves, steam traps and controls throughout the building.

Nelcorp completed the installation of new pole lights in the courtyard and began installing new lights in the gym.

Tri-Valley began roughing in waste and vent lines in the bathrooms. Mid-Atlantic continued removing windows, completing the west side of the building. Workers removed floor tile in the nurse's office, Bassett clinic, and
the halls on both sides of the stage.